Weekly Project Update

Marble Falls Region 13

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Sheet rock started
    Insulation on plumbing pipes inspected last week
    Rough in electrical continues
    Framing new walls 80% complete waiting on replacing damaged sheet rock issue
    Duct work installation 80% complete. Waiting on thru wall issue
    Survived the winter storm and power outages.
Excavation 1.jpg

Blocking for lockers and toilet accessories

NEXT WEEK'S ACTIVITIES

    Steel beam for partition to arrvie and install.
    Sheet rock to continue
    Blocking to continue
    Electrical and low voltage to continue
    Pipe insulation should complete
Excavation 1.jpg
    Partial duct installation should complete.

Insulation of plumbing pipes continues

Excavation 1.jpg

Sheet rock started on hallway walls so tops (tunnel lids) can frame next week.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page