Weekly Project Update

Ojeda Middle School HVAC Replacement

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    RTU 3 and library units set
    Final clean or all work areas inside school and mezzanines
    HVAC startup 93% complete
    All curbs weathered in
    T&B ongoing
    Gas reconnect 75% complete
Excavation 1.jpg

RTU 3 at Aux gym running

NEXT WEEK'S ACTIVITIES

    Complete all unit startup by COB monday
    Complete T&B RTUs and GSHPS
    Complete Gas pipe on roof
    Complete EMA observation report items
    Complete MEP Engineering deficiency lists
Excavation 1.jpg
    Pressure wash roof and water test all curbs

Library air handler units in progress through weekend to start up monday morning

Excavation 1.jpg

Final clean through mezzanines

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.