THIS WEEK'S ACCOMPLISHMENT

    MAUs started up
    Gad connections made and holding test pressure
    MAU controls with Factory Start-up sequence ongoing
    Completed FA tie in for MAUs
    MAU Duct insulation/inspection
Excavation 1.jpg

New MAU ductwork

NEXT WEEK'S ACTIVITIES

    Plumbing inspection on Gas
    Confirm dimensions for new shop drawings on curb adapters
    Coordinate new lift plan/schedule for thanksgiving break
Excavation 1.jpg

Existing HRU curbs capped ready to receive new units

Excavation 1.jpg

MAUs 1 and 2 installed