Weekly Project Update
Ojeda Middle School HVAC Replacement

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- MAUs started up
- Gad connections made and holding test pressure
- MAU controls with Factory Start-up sequence ongoing
- Completed FA tie in for MAUs
- MAU Duct insulation/inspection
-

New MAU ductwork
NEXT WEEK'S ACTIVITIES
- Plumbing inspection on Gas
- Confirm dimensions for new shop drawings on curb adapters
- Coordinate new lift plan/schedule for thanksgiving break
-
-

-
Existing HRU curbs capped ready to receive new units

MAUs 1 and 2 installed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.