Weekly Project Update

Ojeda Middle School HVAC Replacement

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    RTU demo phase 2 started
    RTU curb swap out phase 1 complete
    Welding completed for new MAUs and curbs set
    Admin area split system swap-out ongoing
    Controls and power reconnection completed for GSHPs
Excavation 1.jpg

New condensers for admin area split systems

NEXT WEEK'S ACTIVITIES

    Complete split systems installation for the admin area
    Demo remainder of RTU phase 2 curbs
    Begin flashing in new curbs for RTU phase 2
    Begin installing pumps in the 500-800 mezzanines
    Begin work on roof gas lines
Excavation 1.jpg

New RTU phase 2 curbs

Excavation 1.jpg

Crane removing RTU and flying up new curb

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.