top of page


Weekly Project Update
Ojeda Middle School HVAC Replacement

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- RTU demo phase 2 started
- RTU curb swap out phase 1 complete
- Welding completed for new MAUs and curbs set
- Admin area split system swap-out ongoing
- Controls and power reconnection completed for GSHPs
-

New condensers for admin area split systems
NEXT WEEK'S ACTIVITIES
- Complete split systems installation for the admin area
- Demo remainder of RTU phase 2 curbs
- Begin flashing in new curbs for RTU phase 2
- Begin installing pumps in the 500-800 mezzanines
- Begin work on roof gas lines

-
New RTU phase 2 curbs

Crane removing RTU and flying up new curb
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page