top of page


Weekly Project Update
Ojeda Middle School HVAC Replacement

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- All RTUs arrived onsite and set
- Remaining geo pumps installed onto GSHPS
- Library split system units arrived onsite and flown to roof
- Tile behind fryer hood in kitchen complete
- RTU startup 25% complete
- Test and Balance started in 700 wing

RTU being set
NEXT WEEK'S ACTIVITIES
- Complete Test and Balance all GSHPs
- Complete Test and Balance on split systems and begin RTUs
- Complete unit swaps for the library
- Complete startup on all GSHPS monday
- Complete startup of all RTUs

- Begin installing controls on RTUs
Library condensers ready for swap next week

Lower roof over common areas with New RTUs set
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page