Weekly Project Update

Ojeda Middle School HVAC Replacement

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    All RTUs arrived onsite and set
    Remaining geo pumps installed onto GSHPS
    Library split system units arrived onsite and flown to roof
    Tile behind fryer hood in kitchen complete
    RTU startup 25% complete
    Test and Balance started in 700 wing
Excavation 1.jpg

RTU being set

NEXT WEEK'S ACTIVITIES

    Complete Test and Balance all GSHPs
    Complete Test and Balance on split systems and begin RTUs
    Complete unit swaps for the library
    Complete startup on all GSHPS monday
    Complete startup of all RTUs
Excavation 1.jpg
    Begin installing controls on RTUs

Library condensers ready for swap next week

Excavation 1.jpg

Lower roof over common areas with New RTUs set

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.