top of page


Weekly Project Update
Ojeda Middle School HVAC Replacement

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- Fryer hood removed
- RTU curb swap ongoing
- Admin Split systems ongoing
- All GSHP duct work complete
- Admin controls and power ongoing
- Began installation of pumps and hoses on the GSHPSs

Return air canvas installed on existing ductwork where none was present
NEXT WEEK'S ACTIVITIES
- Start-up all admin units
- Fly remaining curbs to the roof
- Begin installing new RTUs
- Complete installation of RTU curbs
- Close wall and ceiling behind fryer hood

- Start up 800 wing GSHPs
Area behind fryer hood after demo

Admin mezzanine with new units
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page