Weekly Project Update

Ojeda Middle School HVAC Replacement

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Fryer hood removed
    RTU curb swap ongoing
    Admin Split systems ongoing
    All GSHP duct work complete
    Admin controls and power ongoing
    Began installation of pumps and hoses on the GSHPSs
Excavation 1.jpg

Return air canvas installed on existing ductwork where none was present

NEXT WEEK'S ACTIVITIES

    Start-up all admin units
    Fly remaining curbs to the roof
    Begin installing new RTUs
    Complete installation of RTU curbs
    Close wall and ceiling behind fryer hood
Excavation 1.jpg
    Start up 800 wing GSHPs

Area behind fryer hood after demo

Excavation 1.jpg

Admin mezzanine with new units

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.