Weekly Project Update

PFISD Safety And Security Upgrades

Placeholder

Keith Farrell

THIS WEEK'S ACCOMPLISHMENT

    Installed Two Center Corridor Door Frames at Delco Elementary
    Installed Two Center Corridor Door Frames at River Oaks Elementary.
    Pulled Access Control Cable to Four Corridors at Weiland Elementary
    Pulled Access Control Cable to 50% of new Openings at Windermere Elementary
    Installed Pathway Sleeves at Parmer Lane, Barron, and Weiland Elementary
Excavation 1.jpg

Framing New Center Corridor Door Frame at Delco Elementary

NEXT WEEK'S ACTIVITIES

    Continue Pulling Access Control wire at Windermere Elementary.
    Pull Access Control at Riojas Elementary
Excavation 1.jpg

Installing Pathway Sleeves For Access Control at Barron Elementary

Excavation 1.jpg

Installing Sheetrock at New Corridor Door Frames at Delco Elementary

LOOK AHEAD SCHEDULE