Weekly Project Update
PFISD Safety And Security Upgrades

Keith Farrell
THIS WEEK'S ACCOMPLISHMENT
- Installed Two Center Corridor Door Frames at Delco Elementary
- Installed Two Center Corridor Door Frames at River Oaks Elementary.
- Pulled Access Control Cable to Four Corridors at Weiland Elementary
- Pulled Access Control Cable to 50% of new Openings at Windermere Elementary
- Installed Pathway Sleeves at Parmer Lane, Barron, and Weiland Elementary
-

Framing New Center Corridor Door Frame at Delco Elementary
NEXT WEEK'S ACTIVITIES
- Continue Pulling Access Control wire at Windermere Elementary.
- Pull Access Control at Riojas Elementary
-
-
-

-
Installing Pathway Sleeves For Access Control at Barron Elementary

Installing Sheetrock at New Corridor Door Frames at Delco Elementary
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.