THIS WEEK'S ACCOMPLISHMENT

    PIERS/FOOTERS POURED
    CANOPY COLUMNS,BEAMS INSTALLED
    PAVERS INSTALLED
Excavation 1.jpg

PIER READY TO BE POURED

NEXT WEEK'S ACTIVITIES

    CANOPY INSTALLATION COMPLETED
    SCHEDULE SIDEWALK POUR
    CLEANUP AND REDUCE WORK AREA FOOTPRINT
Excavation 1.jpg

FINAL GRADING FOR PAVERS

Excavation 1.jpg

PAVERS INSTALLED/CLEANUP TO FOLLOW