THIS WEEK'S ACCOMPLISHMENT

    INSTALLED CONSTRUCTION FENCE
    REMOVED TALLOW TREE
    REMOVED PAVERS
    REMOVED SIDEWALKS
Excavation 1.jpg

PAVER REMOVAL

NEXT WEEK'S ACTIVITIES

    REROUT EXISTING WATER LINE
    POUR FOOTERS FOR CANOPY
    CANOPY INSTALLATION TO BEGIN
Excavation 1.jpg

TALLOW TREE REMOVAL

Excavation 1.jpg

SITE SECURED, PAVERS REMOVED

LOOK AHEAD SCHEDULE