Weekly Project Update

RAWSON SAUNDERS SCHOOL CANOPY

Placeholder

Pat Tims

THIS WEEK'S ACCOMPLISHMENT

    PIERS/FOOTERS POURED
    CANOPY COLUMNS INSTALLED
    CANOPY BEAMS INSTALLED
    PAVERS INSTALLED
Excavation 1.jpg

PIER REINFORCING STEEL IN PLACE

NEXT WEEK'S ACTIVITIES

    FINISH PAVER CLEANUP
    CANOPY INSTALLATION COMPLETED
    CLEANUP AREA/REDUCE WORKING AREA FOOTPRINT
    SCHEDULE SIDEWALK POUR
Excavation 1.jpg

FINAL GRADING FOR PAVERS

Excavation 1.jpg

PAVERS SET, SAND CLEANUP TO FOLLOW

LOOK AHEAD SCHEDULE