THIS WEEK'S ACCOMPLISHMENT
- Start-up FCU's in Section 'D' and 'C'
- Cont. roofing West of Gym; Install Final Cap Sheet @ Cafeteria
- Cont. Fire Alarm Rough; Install Back-boxes for Devices
- Receive HRU #1
- Complete all RTU & HRU Curb Installation
- Set RTU #11 for MDF Room

Final Roof Cap Sheet @ A-01 CAFETERIA
NEXT WEEK'S ACTIVITIES
- Start-up Remaining FCU's in Section 'B' and 'A'
- Set all RTU's on Roof Curbs
- Complete Duct Cleaning
- Complete Duct Installation
- Continue Ceiling & Tile Reinstallation

- Start Final Cleaning in South Wing - Section C,D,E
HRU #1 Being Unloaded

Parapet Wall Prep to Receive Metal Wall Panels
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.