Weekly Project Update

RRISD - FOREST CREEK ES RENOVATION

Placeholder

Nathan Barry

THIS WEEK'S ACCOMPLISHMENT

    Start-up FCU's in Section 'D' and 'C'
    Cont. roofing West of Gym; Install Final Cap Sheet @ Cafeteria
    Cont. Fire Alarm Rough; Install Back-boxes for Devices
    Receive HRU #1
    Complete all RTU & HRU Curb Installation
    Set RTU #11 for MDF Room
Excavation 1.jpg

Final Roof Cap Sheet @ A-01 CAFETERIA

NEXT WEEK'S ACTIVITIES

    Start-up Remaining FCU's in Section 'B' and 'A'
    Set all RTU's on Roof Curbs
    Complete Duct Cleaning
    Complete Duct Installation
    Continue Ceiling & Tile Reinstallation
Excavation 1.jpg
    Start Final Cleaning in South Wing - Section C,D,E

HRU #1 Being Unloaded

Excavation 1.jpg

Parapet Wall Prep to Receive Metal Wall Panels

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.