Weekly Project Update
RRISD - FOREST CREEK ES RENOVATION

Nathan Barry
THIS WEEK'S ACCOMPLISHMENT
- Completed 95% Start-up of all Classroom AC Units
- Continue Roofing Demo / Dry-in; Continue Final Cap Sheet
- Continue Interior Exhaust Fan Ductwork
- Set all (12) RTU's on Roof
- Start Fire Alarm Device Installation
- Completed 75% of Exterior Caulking

Install Rigid Insulation Board inside Bottom of RTU Curb
NEXT WEEK'S ACTIVITIES
- Start-up RTU's Beginning with RTU #1, #2, #11
- Complete all Ductwork
- Re-install Ceiling / Tile
- Install Fire Alarm Control Panel
- Continue Roof Demo / Dry-in; Cont. Final Cap Sheet

- Cont. Final Cleaning
Roof Water Hydrant 1 of 4 - Typical

Setting 1 of 12 RTU's on Friday 7-22-2022
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.