THIS WEEK'S ACCOMPLISHMENT
- Continue FCU Connection: Duct, Controls
- Continue Installation of Classroom Condensers / Refrigerant Piping
- Continue Duct Modifications at Classrooms
- Continue Roof 1st Phase Demo / Dry-in and Electric Curb / T-Top Installation
- Continue Roof Drain Replacement
- Continue Fire Alarm Wire Installation

Electric Curbs and T-Tops Set
NEXT WEEK'S ACTIVITIES
- Complete Setting of HRU Curbs
- Continue Demo / Dry-in Roofing
- Start Final Roof Cap Sheet
- Finish Classroom Condenser Installation, Piping and Controls
- Continue Classroom Duct Modifications

- Continue Fire Alarm Installation
Last (16) Classroom Condensers Delivered