top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

RRISD Forest Creek ES

Placeholder

Nathan Barry

THIS WEEK'S ACCOMPLISHMENT

    Continue FCU Connection: Duct, Controls
    Continue Installation of Classroom Condensers / Refrigerant Piping
    Continue Duct Modifications at Classrooms
    Continue Roof 1st Phase Demo / Dry-in and Electric Curb / T-Top Installation
    Continue Roof Drain Replacement
    Continue Fire Alarm Wire Installation
Excavation 1.jpg

Electric Curbs and T-Tops Set

NEXT WEEK'S ACTIVITIES

    Complete Setting of HRU Curbs
    Continue Demo / Dry-in Roofing
    Start Final Roof Cap Sheet
    Finish Classroom Condenser Installation, Piping and Controls
    Continue Classroom Duct Modifications
Excavation 1.jpg
    Continue Fire Alarm Installation

Last (16) Classroom Condensers Delivered

Excavation 1.jpg

Typical Day of Roofing

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page