Weekly Project Update

RRISD Forest Creek ES

Placeholder

Nathan Barry

THIS WEEK'S ACCOMPLISHMENT

    Cont. Roof Demo / Dry-in; Start Finish Cap Sheet
    Cont. Roof Drain Installation; Install Roof Water Hydrant
    Demo Skylight; Raise Curb for new Skylight
    Complete Structural Steel Support for HRU Curbs; Set Curbs
    Start-up (11) Classroom FCU’s
    Start Ceiling Grid / Tile Reinstallation
Excavation 1.jpg

Old Skylight Removed; Curb Assembly Raised

NEXT WEEK'S ACTIVITIES

    Start-up (18) FCU’s @ Section C, D
    Cont. Duct Installation @ Section ‘A’
    Cont. Roof Operations
    Set RTU’s
    Continue Ceiling Grid & Tile Reinstallation
Excavation 1.jpg
    Start Rough Final Cleaning @ Section ‘E’

Roofer Torching Down Base Sheet – Typical

Excavation 1.jpg

Early Morning Roofing

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.