THIS WEEK'S ACCOMPLISHMENT
- Cont. Roof Demo / Dry-in; Start Finish Cap Sheet
- Cont. Roof Drain Installation; Install Roof Water Hydrant
- Demo Skylight; Raise Curb for new Skylight
- Complete Structural Steel Support for HRU Curbs; Set Curbs
- Start-up (11) Classroom FCU’s
- Start Ceiling Grid / Tile Reinstallation

Old Skylight Removed; Curb Assembly Raised
NEXT WEEK'S ACTIVITIES
- Start-up (18) FCU’s @ Section C, D
- Cont. Duct Installation @ Section ‘A’
- Cont. Roof Operations
- Set RTU’s
- Continue Ceiling Grid & Tile Reinstallation

- Start Rough Final Cleaning @ Section ‘E’