Weekly Project Update
RRISD Great Oaks ES

Ian Doyle
THIS WEEK'S ACCOMPLISHMENT
- Finished Installing HVAC Units / South Wing
- Finished Installing Outside Air Duct Work / South Wing
- Finished Re-Installing Ceiling Grid and Tile / North Wing
- Continue Installing Exhaust Fan Duct Work / North Wing
- Start Up HVAC Units / North Wing
- Start Installing HVAC Units / Admin Wing

Re-Installing Ceiling Grid and Tile
NEXT WEEK'S ACTIVITIES
- Finish Start Up of HVAC Units / North Wing
- Finish Installing HVAC Units / Admin Wing
- Finish Re-Installing Ceiling Grid and Tile / South Wing
- Start Up HVAC Units / South Wing
- Start Cleaning North Wing Classrooms and Day Care

- Start Preparing to Install HVAC Roof Top Units
Installing HVAC Units / Admin Wing

North Wing Classroom Ceiling Installed and Ready for Cleaning