Weekly Project Update

RRISD Great Oaks ES

Placeholder

Ian Doyle

THIS WEEK'S ACCOMPLISHMENT

    Finished Installing HVAC Units / South Wing
    Finished Installing Outside Air Duct Work / South Wing
    Finished Re-Installing Ceiling Grid and Tile / North Wing
    Continue Installing Exhaust Fan Duct Work / North Wing
    Start Up HVAC Units / North Wing
    Start Installing HVAC Units / Admin Wing
Excavation 1.jpg

Re-Installing Ceiling Grid and Tile

NEXT WEEK'S ACTIVITIES

    Finish Start Up of HVAC Units / North Wing
    Finish Installing HVAC Units / Admin Wing
    Finish Re-Installing Ceiling Grid and Tile / South Wing
    Start Up HVAC Units / South Wing
    Start Cleaning North Wing Classrooms and Day Care
Excavation 1.jpg
    Start Preparing to Install HVAC Roof Top Units

Installing HVAC Units / Admin Wing

Excavation 1.jpg

North Wing Classroom Ceiling Installed and Ready for Cleaning