THIS WEEK'S ACCOMPLISHMENT

    Finished Start Up of HVAC Units / North Wing
    Finished Re-Installing Ceiling Grid and Tile / South Wing
    Finished Cleaning North Wing Classrooms and Daycare
    Continued Start Up of HVAC Units / South Wing
    Started Cleaning South Wing Classrooms
    Started Installing HVAC Roof Top Units
Excavation 1.jpg

Admin Wing HVAC Split System Rough Electrical Installation

NEXT WEEK'S ACTIVITIES

    Finish Start Up of HVAC Units / South Wing
    Finish Cleaning South Wing Classrooms
    Finish Installing HVAC Roof Top Units
    Continue Start Up of HVAC Units / Admin Wing
    Start Re-Installing Ceiling Grid and Tile / Admin Wing
Excavation 1.jpg
    Start Cleaning Admin Wing Offices

Admin Wing Skylights Installed Over Art Classroom

Excavation 1.jpg

HVAC Roof Top Units Installed on Admin Wing Roof