Weekly Project Update
RRISD Great Oaks ES

Ian Doyle
THIS WEEK'S ACCOMPLISHMENT
- Finished Installing Exhaust Fan Duct Work
- Finished Installing Final Roof System Layers
- Finished Installing Outside Air Duct Work / North Wing
- Continued Installing HVAC Units / South Wing
- Started Installing Outside Air Duct Work / South Wing
- Started Insulating HVAC Equipment

In-Line Exhaust Fan Installation
NEXT WEEK'S ACTIVITIES
- Finish Installing HVAC Units / South Wing
- Continue Installing Outside Air Duct Work / South Wing
- Continue Insulating HVAC Equipment
- Start Up HVAC Units North Wing
- Start Installing HVAC Units / Admin Wing

- Start Re-Installing Ceiling Grid and Tile / North Wing
HVAC Control Wires Installed and Refrigerant Lines Insulated

New Classroom Outside Air Duct Installed and Insulated
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.