top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

RRISD Great Oaks ES

Placeholder

Ian Doyle

THIS WEEK'S ACCOMPLISHMENT

    Finished Installing Exhaust Fan Duct Work
    Finished Installing Final Roof System Layers
    Finished Installing Outside Air Duct Work / North Wing
    Continued Installing HVAC Units / South Wing
    Started Installing Outside Air Duct Work / South Wing
    Started Insulating HVAC Equipment
Excavation 1.jpg

In-Line Exhaust Fan Installation

NEXT WEEK'S ACTIVITIES

    Finish Installing HVAC Units / South Wing
    Continue Installing Outside Air Duct Work / South Wing
    Continue Insulating HVAC Equipment
    Start Up HVAC Units North Wing
    Start Installing HVAC Units / Admin Wing
Excavation 1.jpg
    Start Re-Installing Ceiling Grid and Tile / North Wing

HVAC Control Wires Installed and Refrigerant Lines Insulated

Excavation 1.jpg

New Classroom Outside Air Duct Installed and Insulated

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page