Weekly Project Update

Region 13 La Grange

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Started installing HVAC Grilles
    Ceiling grid complete Area C
    Tape and float started on Area A walls
    HVAC rough in area A complete
    Ceramic tile in shower room complete
    Condensing units for mini splits have been set
Excavation 1.jpg

View of corridor outside of MDF room

NEXT WEEK'S ACTIVITIES

    Set out plumbing fixtures
    Float floors in area C
    Complete area B furrdowns and begin installing ceiling grid
    Start up existing HVAC systems and new mini splits
    Complete HVAC grille installation
Excavation 1.jpg
    Complete first coat of paint in all areas

Framing progress of Operable partition furrdowns

Excavation 1.jpg

View of Break room with furrdowns to receive vending machines and millwork

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.