Weekly Project Update
Region 13 La Grange

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- Ductwork rough in 50% complete areas B and C
- One side sheetrock areas B and C complete
- Sawcutting for underslab plumbing and embed plates complete
- Framing for corridor ceilings started
- Electrical in-wall rough areas B and C 80% complete
- Overhead electrical rough areas B and C 50% complete

Sawcutting for plumbing trench
NEXT WEEK'S ACTIVITIES
- Begin underslab plumbing rough
- In-wall inspection area C
- Insulate and two-side walls area C
- In-wall inspection Area B
- Set embed plates for steel

- Complete ductwork rough-in area B
Ductwork rough-in Area B

Corridor ceilings framing