Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Ductwork rough in 50% complete areas B and C
    One side sheetrock areas B and C complete
    Sawcutting for underslab plumbing and embed plates complete
    Framing for corridor ceilings started
    Electrical in-wall rough areas B and C 80% complete
    Overhead electrical rough areas B and C 50% complete
Excavation 1.jpg

Sawcutting for plumbing trench

NEXT WEEK'S ACTIVITIES

    Begin underslab plumbing rough
    In-wall inspection area C
    Insulate and two-side walls area C
    In-wall inspection Area B
    Set embed plates for steel
Excavation 1.jpg
    Complete ductwork rough-in area B

Ductwork rough-in Area B

Excavation 1.jpg

Corridor ceilings framing