Weekly Project Update
Region 13 La Grange

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- Steel columns and beams installed
- Corridor ceilings 3 layers of sheet rock 90% complete
- Tape/float started on corridor ceilings
- Area A bathrooms inspected and sheetrocked
- Plumbing top-out complete
- HVAC rough in started in mezzanine at area C

Restrooms sheetrocked
NEXT WEEK'S ACTIVITIES
- Complete float of area B and corridor ceilings
- Close up remaining walls at steel columns
- Install operable partition track
- Begin framing furrdowns
- Begin ceramic tile installation in restrooms

- Begin grilling out HVAC
Tape and float on corridor ceilings

Steel erected in main classrooms
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.