Weekly Project Update

Region 13 La Grange

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Steel columns and beams installed
    Corridor ceilings 3 layers of sheet rock 90% complete
    Tape/float started on corridor ceilings
    Area A bathrooms inspected and sheetrocked
    Plumbing top-out complete
    HVAC rough in started in mezzanine at area C
Excavation 1.jpg

Restrooms sheetrocked

NEXT WEEK'S ACTIVITIES

    Complete float of area B and corridor ceilings
    Close up remaining walls at steel columns
    Install operable partition track
    Begin framing furrdowns
    Begin ceramic tile installation in restrooms
Excavation 1.jpg
    Begin grilling out HVAC

Tape and float on corridor ceilings

Excavation 1.jpg

Steel erected in main classrooms

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.