Weekly Project Update
Region 13 La Grange

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- Ceiling demo in main space completed
- Above ceiling demo in main space completed
- Wall layout started
- HVAC layout and hanger support installation started
- Electrical demo in main space completed
- Wall demo started

Ceiling demo and above ceiling demo complete
NEXT WEEK'S ACTIVITIES
- Complete remaining demo
- Complete wall layout
- Begin framing offices and classrooms
- Continue HVAC overhead rough in
- Begin electrical overhead rough in

- Sawcut for underslab plymbing
Wall layout started

View from entry doors
LOOK AHEAD SCHEDULE