Weekly Project Update

Region 13 La Grange

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Ceiling demo in main space completed
    Above ceiling demo in main space completed
    Wall layout started
    HVAC layout and hanger support installation started
    Electrical demo in main space completed
    Wall demo started
Excavation 1.jpg

Ceiling demo and above ceiling demo complete

NEXT WEEK'S ACTIVITIES

    Complete remaining demo
    Complete wall layout
    Begin framing offices and classrooms
    Continue HVAC overhead rough in
    Begin electrical overhead rough in
Excavation 1.jpg
    Sawcut for underslab plymbing

Wall layout started

Excavation 1.jpg

View from entry doors

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.