Weekly Project Update
Region 13 Marble Falls

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Ceiling grid 70%
- Air conditioner grilles arrived and are getting insulated prior to installing
- Pulling electrical wire for soon energized circuts.
- Steel openings thru walls completed
- Tape/Float/Paint first coat 75%
- HWH set

Mini units above ceiling hanging waiting on duct work.
NEXT WEEK'S ACTIVITIES
- Grid 95% waiting on chase walls
- Grilles in grid start
- Fire alarm set out in grid and on walls starts.
- Mini split units to pipe and energize
- Tile in bathrooms starts and should get 75% done

- Better confirmation of missing items and when they deliver. Project will slow waiting on delivery.
A/C grilles arrived. Will start install next week.

Grid installed 75%
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.