top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Region 13 Marble Falls

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Ceiling grid 70%
    Air conditioner grilles arrived and are getting insulated prior to installing
    Pulling electrical wire for soon energized circuts.
    Steel openings thru walls completed
    Tape/Float/Paint first coat 75%
    HWH set
Excavation 1.jpg

Mini units above ceiling hanging waiting on duct work.

NEXT WEEK'S ACTIVITIES

    Grid 95% waiting on chase walls
    Grilles in grid start
    Fire alarm set out in grid and on walls starts.
    Mini split units to pipe and energize
    Tile in bathrooms starts and should get 75% done
Excavation 1.jpg
    Better confirmation of missing items and when they deliver. Project will slow waiting on delivery.

A/C grilles arrived. Will start install next week.

Excavation 1.jpg

Grid installed 75%

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page