top of page


Weekly Project Update
Region 13 Marble Falls

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Tape and floated front rooms
- Sanded and textured front rooms
- Primed front rooms
- More duct arrived and installed in rear
- Conduit and wiring in rear
- Completed sheet rock patches in rear, ready for float next week.

Some walls textured ready for paint.
NEXT WEEK'S ACTIVITIES
- Paint first coat on front rooms.
- Start grid in front rooms.
- Prep shower for waterproofing
- Steel framing for a/c duct thru wall
- Tape and float rear rooms.

- Pulling wiring thru conduits.
Door frames and windows protected during paint operations.

Primer being installed on all front rooms. Ready for first coat next week.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.