Weekly Project Update
Region 13 Marble Falls

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Sheet rock arrived ready to install after inspections
- 90% of new water lines run
- 50% of new duct
- 95% of new conduit run
- Patching of existing walls started
- Framing of new walls 90%

Copper piping in walls
NEXT WEEK'S ACTIVITIES
- More wall patching
- Pull electrical wires thru conduits
- More duct work installed
- RTU raised curb ordered and confirmation of 12 week delivery
- Insulation on piping

- Insulation on duct.
Sheet rock arrived for install start next week

Lots of new duct installing
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.