Weekly Project Update

Region 13 Marble Falls

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Sheet rock arrived ready to install after inspections
    90% of new water lines run
    50% of new duct
    95% of new conduit run
    Patching of existing walls started
    Framing of new walls 90%
Excavation 1.jpg

Copper piping in walls

NEXT WEEK'S ACTIVITIES

    More wall patching
    Pull electrical wires thru conduits
    More duct work installed
    RTU raised curb ordered and confirmation of 12 week delivery
    Insulation on piping
Excavation 1.jpg
    Insulation on duct.

Sheet rock arrived for install start next week

Excavation 1.jpg

Lots of new duct installing

LOOK AHEAD SCHEDULE