Weekly Project Update

SIGMA CHI

Greg Berlin

THIS WEEK'S ACCOMPLISHMENT

    EXCAVATED 75% OF ALL GRADE BEAMS
    STARTED ELECTRIC ROUGH
    PASSED PARTIAL INSPECTION ELECTRIC UNDERGROUND
    CLEANED AND PREP EXISTING GRADE BEAM FOR STEEL INSTALLATION
    COMPLETED SUPPLY LINES

WEST, NORTH/SOUTH GRADE BEAM

NEXT WEEK'S ACTIVITIES

    POUR ELEVATOR FLOOR
    START ELEVATOR SHAFT FORM
    PLUMBER TO ROUGH SUMP PUMP AT ELEVATOR
    TIE STEEL IN GRADE BEAMS
    FORM PIER CAPS

EAST, NORTH/SOUTH GRADE BEAM

FOUNDATION STEEL

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.