Weekly Project Update
Spicewood ES

Richard Huddleston
THIS WEEK'S ACCOMPLISHMENT
- Set Rooftop curbs for A/C units 2,3, and 5.
- Complete new electrical panel raceways and wire to bring the MDF room back online.
- Completed installation of Heat pumps, refrigerant lines and controls for classrooms on the 300 wing.
- Completed plumbing rough and inspection at Restroom set A.
- Completed electrical rough in restroom set A
- Installed roof curbs for 10 exhaust fans.

Installing above ceiling air conditioning units above the admin. area.
NEXT WEEK'S ACTIVITIES
- Electrical inspection in restroom set A.
- Cover walls and ceilings with drywall.
- Start tile in restroom set A.
- Set rooftop curbs for A/C units 1 and 4
- Continue steel reinforcement for new rooftop equipment.

- Complete plumbing in restroom set C
Adding steel cross bracing to existing steel roof joist to support rooftop equipment.

Cutting concrete floor in the set B restroom on the 100 wing so new plumbing can be installed.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.