top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Spicewood ES

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Set Rooftop curbs for A/C units 2,3, and 5.
    Complete new electrical panel raceways and wire to bring the MDF room back online.
    Completed installation of Heat pumps, refrigerant lines and controls for classrooms on the 300 wing.
    Completed plumbing rough and inspection at Restroom set A.
    Completed electrical rough in restroom set A
    Installed roof curbs for 10 exhaust fans.
Excavation 1.jpg

Installing above ceiling air conditioning units above the admin. area.

NEXT WEEK'S ACTIVITIES

    Electrical inspection in restroom set A.
    Cover walls and ceilings with drywall.
    Start tile in restroom set A.
    Set rooftop curbs for A/C units 1 and 4
    Continue steel reinforcement for new rooftop equipment.
Excavation 1.jpg
    Complete plumbing in restroom set C

Adding steel cross bracing to existing steel roof joist to support rooftop equipment.

Excavation 1.jpg

Cutting concrete floor in the set B restroom on the 100 wing so new plumbing can be installed.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page