Weekly Project Update
Spicewood ES

Richard Huddleston
THIS WEEK'S ACCOMPLISHMENT
- Cleared plumbing and electrical inspections in restroom set C.
- Received curbs for outside air equipment.
- Installed 4 of 5 RTU curbs and 3 of 4 outside air curbs.
- Completed underground plumbing in restroom set B inspection on Monday
- Started tile work in restroom set A.
- Began reinstalling ceiling grid.

Insulated new ductwork on corridor 500.
NEXT WEEK'S ACTIVITIES
- Reinstall ceiling grid and tile in corridor 500 classrooms.
- Complete plumbing rough in restroom set B.
- Complete drywall in restroom set C
- Install new ceiling grid in corridor 500.
- Start tile work in restroom set C

- Set the last 2 roof curbs and prepare to install rooftop equipment.
Preparing roof to set curb for DOAS 4.

Installed new wall tile at drinking fountain on corridor 500.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.