Weekly Project Update
Spicewood ES

Richard Huddleston
THIS WEEK'S ACCOMPLISHMENT
- Completed drywall in Restroom set C.
- Completed refrigerant line installation for the branch selectors for the VRF systems in the admin and teachers lounge areas.
- Completed tape, float, texture and 1st coat of paint in restroom C.
- Completed steel reinforcement for rooftop equipment.
- Completed drywall on the 100 wing corridor.
- Completed HVAC duct transition from rooftop equipment curb to main trunk lines for RTU 3,4,& 5.

Installed duct drops from rooftop equipment curbs to main trunk lines above ceiling at RTU 4
NEXT WEEK'S ACTIVITIES
- Duct inspection for library and admin area.
- Above ceiling inspection for corridors 400 and 500.
- Set restroom fixtures in set A restrooms.
- Receive CME 1 and 2.
- Set RTUs 1-5 and CME 1&2.

- Final clean classrooms 100 &,500
Began installation of ceiling grid and new wainscoting in corridor 200.

Installed ceiling grid and new wainscoting in corridor 500
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.