Weekly Project Update

Spicewood ES

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Completed drywall in Restroom set C.
    Completed refrigerant line installation for the branch selectors for the VRF systems in the admin and teachers lounge areas.
    Completed tape, float, texture and 1st coat of paint in restroom C.
    Completed steel reinforcement for rooftop equipment.
    Completed drywall on the 100 wing corridor.
    Completed HVAC duct transition from rooftop equipment curb to main trunk lines for RTU 3,4,& 5.
Excavation 1.jpg

Installed duct drops from rooftop equipment curbs to main trunk lines above ceiling at RTU 4

NEXT WEEK'S ACTIVITIES

    Duct inspection for library and admin area.
    Above ceiling inspection for corridors 400 and 500.
    Set restroom fixtures in set A restrooms.
    Receive CME 1 and 2.
    Set RTUs 1-5 and CME 1&2.
Excavation 1.jpg
    Final clean classrooms 100 &,500

Began installation of ceiling grid and new wainscoting in corridor 200.

Excavation 1.jpg

Installed ceiling grid and new wainscoting in corridor 500

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.