THIS WEEK'S ACCOMPLISHMENT
- Start Site Grading
- Framing & Trusses Fitness Area
- CMU Columns South Apparatus Bay
- CMU Columns North Apparatus Bay
- DensGlass Sheathing North Side Living Quaters
-

Ready For Waterproofing
NEXT WEEK'S ACTIVITIES
- Trusses Above Mezzanine
- Structural Tube at Bay Doors
- Metal Stud Framing at Laundry & Kitchen
- Complete Site Grading
- Apparatus Bay Cover Board and Water Shield

-
DensGlass South Side Living Quarters

Ready for Site Concrete
LOOK AHEAD SCHEDULE