Weekly Project Update
TCESD 2 STATION 6

Jeff Krueger
THIS WEEK'S ACCOMPLISHMENT
- Concrete Paving Parking & Fire Lane Complete
- LQ Interior Framing
- North Fire Lane Forms & Reinforcing Steel
- Wood Blocking at AB Facia
- Electrical & Plumbing Interior Wall Rough In
-

LQ Interior Walls Underway
NEXT WEEK'S ACTIVITIES
- North Fire Lane Concrete Paving
- Structural Steel
- Concrete Placement at Approaches
- CMU Walls East AB
- AB Overhead Electrical Piping

-
AB Wood Blocking

Concrete Paving Wrapping Up
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.