Weekly Project Update
TCESD 2 STATION 6

Jeff Krueger
THIS WEEK'S ACCOMPLISHMENT
- Concrete Paving Forms Set 1st & 2nd Pour
- Concrete Paving Reinforcing Steel 1st & 2nd Pour
- Trusses at LQ
- Dens Shield at LQ
-
-

LQ Dens Glass Progress
NEXT WEEK'S ACTIVITIES
- Concrete Paving Pour 1st & 2nd
- Structural Steel
- CMU Masonry Walls
- Electrical Wall Rough In
- Plumbing Wall Rough In

- Wood Blocking at AB Roof
Lime Stabilization Complete

Ready For Concrete
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.