Weekly Project Update

TCESD 2 STATION 6

Placeholder

Jeff Krueger

THIS WEEK'S ACCOMPLISHMENT

    Retaining Wall Concrete Placement
    Retaining Wall Wreck Forms
    Metal Stud Framing at AB
    Exterior Sheathing Material On-site
    Hollow Metal Door Frames Set at AB
Excavation 1.jpg

Exterior Sheathing Underway

NEXT WEEK'S ACTIVITIES

    Exterior Sheathing Install
    Concrete Paving Grading
    Irrigation Sleeves
    Retaining Wall Backfill
    CMU Wall Install
Excavation 1.jpg

AB Metal Stud Framing

Excavation 1.jpg

Retaining Wall Ready to Backfill

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.