Weekly Project Update

TCESD 2 STATION 6

Placeholder

Jeff Krueger

THIS WEEK'S ACCOMPLISHMENT

    On Site Wastewater Line Complete
    Fire Lines Complete
    Grade Beam Concrete Placement at LQ
    All Manholes Installed & Tested
    Rain Collection Tank Set
Excavation 1.jpg

Rain Collection Tank Set

NEXT WEEK'S ACTIVITIES

    Excavate Grade Beams at AB
    Set Grade Beam Forms at AB
    Install Soil Retainers at LQ
    Back Fill Grade Beams at LQ
    Grade Beam Reinforcing Steel at AB
Excavation 1.jpg

On Site Wastewater Lines Wrapped Up

Excavation 1.jpg

LQ GB Concrete Underway

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.