THIS WEEK'S ACCOMPLISHMENT
- On Site Wastewater Line Complete
- Fire Lines Complete
- Grade Beam Concrete Placement at LQ
- All Manholes Installed & Tested
- Rain Collection Tank Set
-

Rain Collection Tank Set
NEXT WEEK'S ACTIVITIES
- Excavate Grade Beams at AB
- Set Grade Beam Forms at AB
- Install Soil Retainers at LQ
- Back Fill Grade Beams at LQ
- Grade Beam Reinforcing Steel at AB

-
On Site Wastewater Lines Wrapped Up

LQ GB Concrete Underway