Weekly Project Update
TCESD 2 STATION 6

Jeff Krueger
THIS WEEK'S ACCOMPLISHMENT
- Fire Lines Complete
- Site Storm Pipe Complete
- Pier Drilling & Concrete Complete
- Grade Beam Excavation
- Off Site Sanitary Sewer Line
- Grade Beam Reinforcing On Site

Fire Line North Side
NEXT WEEK'S ACTIVITIES
- Sanitary Sewer Line
- Grade Beam Excavation
- Grade Beam Forms
- Grade Beam Reinforcing
-

-
Sanitary Sewer Line

Grade Beam Excavation Underway
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.