Weekly Project Update
TCESD 2 STATION 6

Jeff Krueger
THIS WEEK'S ACCOMPLISHMENT
- Water Taps
- Quality Control Form Check
- AB Forms Underway
- Wastewater Line 60%
- Install Backflow Vault
- Install Final Fire Hydrant

Manhole #3 Installed at Weiss Ln.
NEXT WEEK'S ACTIVITIES
- Complete LQ Reinforcing Steel
- Close Up LQ Grade Beams
- Wastewater Line
- Set LQ Anchor Bolts
- LQ Grade Beam Concrete Placement

-
Water Line Taps Are Complete

LQ Reinforcing Steel Underway
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.