Weekly Project Update
TCESD 2 STATION 6

Jeff Krueger
THIS WEEK'S ACCOMPLISHMENT
- AB Decking
- AB Approaches Concrete Placement
- Retaining Wall Reinforcing Steel Installed & Inspected
- LQ CMU Walls
- AB Hollow Metal Frames
- Retaining Wall Footer Concrete Placement

AB Decking Complete
NEXT WEEK'S ACTIVITIES
- Retaining Wall Forms
- Retaining Wall Concrete Placement
- AB Fascia Blocking
- AB CMU Walls
- Exterior Metal Stud Framing

-
Retaining Wall Ready for Concrete

Progressing
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.