Weekly Project Update

TCESD 2 STATION 6

Placeholder

Jeff Krueger

THIS WEEK'S ACCOMPLISHMENT

    AB Backfill
    LQ Lug Forms
    AB Plumbing Rough In Underway
    AB Electrical Rough In
    Sanitary Sewer Irrigation
Excavation 1.jpg

LQ Lug Forms Wrapping Up

NEXT WEEK'S ACTIVITIES

    LQ Termite Pre-Treat
    LQ Void Forms
    LQ Vapor Barrier
    LQ Reinforcing Steel
    AB Trough Drains
Excavation 1.jpg

AB Plumbing Rough In

Excavation 1.jpg

Final Steps For Concrete Placement

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.