Weekly Project Update

TCESD 2 STATION 6

Placeholder

Jeff Krueger

THIS WEEK'S ACCOMPLISHMENT

    Masonry Layout
    Masonry Scaffolds & Stock Material
    Metal Stud Wall Layout
    Camera Sanitary Sewer Lines
    Start Door Frames at Masonry Walls
Excavation 1.jpg

Mason Ready To Go

NEXT WEEK'S ACTIVITIES

    Retaining Wall Excavation
    Retaining Wall Reinforcing Steel
    Masonry Walls
    Exterior Metal Stud Framing
    AB Approach Forms & Reinforcing Steel
Excavation 1.jpg

LQ Metal Stud Wall Layout

Excavation 1.jpg

Masonry Walls Underway

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.