Weekly Project Update

Region 13 La Grange

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Operable partition track installed
    All sheetrock ceilings completed
    Painting started on sheetrock ceilings
    Ceramic tile in restrooms complete
    Area A two side sheetrock on walls complete
    Area C ductwork rough in Mezzanine complete
Excavation 1.jpg

Ceramic tile in restrooms

NEXT WEEK'S ACTIVITIES

    Complete ceramic tile in shower
    HVAC start-up
    Compete furrdowns in area B around steel beams
    Complete ceiling grid area C
    Begin ceiling grid area B
Excavation 1.jpg
    Complete first coat of paint Areas C and B

Operable partition track installed

Excavation 1.jpg

Tape, Float, Prime, Paint progress in corridors

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.