top of page


Weekly Project Update
Region 13 La Grange

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- Operable partition track installed
- All sheetrock ceilings completed
- Painting started on sheetrock ceilings
- Ceramic tile in restrooms complete
- Area A two side sheetrock on walls complete
- Area C ductwork rough in Mezzanine complete

Ceramic tile in restrooms
NEXT WEEK'S ACTIVITIES
- Complete ceramic tile in shower
- HVAC start-up
- Compete furrdowns in area B around steel beams
- Complete ceiling grid area C
- Begin ceiling grid area B

- Complete first coat of paint Areas C and B
Operable partition track installed

Tape, Float, Prime, Paint progress in corridors
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page