HYDE PARK FIELDHOUSE PHASE 1

THIS WEEK'S ACCOMPLISHMENT

    Patio Grade Beams 80%
    Post Holes for New Fence
    Post Set for New Fence

Ready for Concrete

NEXT WEEK'S ACTIVITIES

    Install Vapor Barrier
    Install Reinforcing Steel
    Set Patio Foundation Forms
    Set Anchor Bolts

Jack Hammers Making Progress

Patio Foundation Underway