Weekly Project Update

BBTCS Marble Falls Renovations 10-14-2022

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    first coat of paint in Area 1 reception, waiting area, and telemed
    Accent walls painted in Area 1 Conference Room and restrooms
    Began installing ceiling grid in Area 1 Telemed offices and waiting area
    Area 1 offices cleaned and ready for staff to move back in
Excavation 1.jpg

Conference Room accent wall

NEXT WEEK'S ACTIVITIES

    A/C grill relocation
    Sprinkler head relocation
    Complete ceiling grid installation
    Begin Telemed, Reception, and waiting area flooring
Excavation 1.jpg

Area 1 offices ready for staff

Excavation 1.jpg

1st coat of paint in waiting area

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.