Weekly Project Update

CEDAR RIDGE CTE

Placeholder

Keith Farrell

THIS WEEK'S ACCOMPLISHMENT

    Completed piping in two new roof top AC units
    Completed fire Proofing of new steel
    Pre wire for speakers is complete
    Pulled data wires to health science area
    Started two AC units
    Removed temporary walls
Excavation 1.jpg

Wiring for display boards in bistro

NEXT WEEK'S ACTIVITIES

    Complete Chill water piping in bistro
    Start last two AC units
    Complete Data wiring
    Set roof top exhaust fans
    Wire roof top exhaust fans
Excavation 1.jpg
    Set millwork

Fire proofing on steel bar joist

Excavation 1.jpg

Removed temporary walls

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.