THIS WEEK'S ACCOMPLISHMENT
- Removed old floor sinks
- Cut Concrete for new floor sinks
- Stood structural steel
- Removed existing columns
- Passed welding inspection
- Stared ceiling grid

New steel for roll up doors
NEXT WEEK'S ACTIVITIES
- Finish ceiling grid
- Frame Walls
- pour back concrete where old sinks were removed
- Electric and data rough in
- Plumbing rough in

- Steel angles under floor for new sink supports
Holes for new sinks

Ceiling grid started
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.