THIS WEEK'S ACCOMPLISHMENT

    Relocated Fire Sprinklers for New Sheetrock Ceilings
    Completed Electrical Rough
    Continued Access Control Pathways
    Completed Demo of Exterior CMU for Storefront New Entrance
Excavation 1.jpg

Rough Opening For New Storefront Entrance

NEXT WEEK'S ACTIVITIES

    Complete Access Control Pathways
    Install Interior Hollow Metal Door Frame
    Sheetrock Walls and Ceilings
    Begin Tape and Float of New Walls and Ceilings
Excavation 1.jpg

Relocated Fire Sprinklers

Excavation 1.jpg

Rough Opening for New Storefront Entrance

LOOK AHEAD SCHEDULE