THIS WEEK'S ACCOMPLISHMENT
- INSTALLED PVC CLEANOUTS
- INSTALLED LARGE CLEANOUT
- INSTALLED PVC DRAIN TO SWELL
- ROUTED IRRIGATION LINES OUTSIDE PLAYSCAPE
-
-

ANGULAR LIMESTONE IN PLACE
NEXT WEEK'S ACTIVITIES
- CONNECT IRRIGATION CONTROL WIRING
- BACKFILL IRRIGATION TRENCH
- REPAIR SIDEWALK
- GRADE AREA AROUND PLAYSCAPE
- INSTALL RUBBLE AT DRAIN

-