Weekly Project Update

FORREST TRAILS PLAYSCAPE IMPROVEMENTS

Placeholder

Pat Tims

THIS WEEK'S ACCOMPLISHMENT

    INSTALLED PVC CLEANOUTS
    INSTALLED LARGE CLEANOUT
    INSTALLED PVC DRAIN TO SWELL
    ROUTED IRRIGATION LINES OUTSIDE PLAYSCAPE
Excavation 1.jpg

ANGULAR LIMESTONE IN PLACE

NEXT WEEK'S ACTIVITIES

    CONNECT IRRIGATION CONTROL WIRING
    BACKFILL IRRIGATION TRENCH
    REPAIR SIDEWALK
    GRADE AREA AROUND PLAYSCAPE
    INSTALL RUBBLE AT DRAIN
Excavation 1.jpg

LARGE CLEANOUT

Excavation 1.jpg

PVC CLEANOUTS

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.