Nathan Barry
THIS WEEK'S ACCOMPLISHMENT
- Complete New Mechanical Yard Housekeeping Pads
- Install Temporary Chain-link Fencing @ New Mech. Yards
- Complete Ceiling Grid @ 12' AFF Bays in GATHERING ROOM
- Complete Tape-Float-Sanding of all walls
- Set All but (3) Condensers
- Extend Refrigerant Lines to Exterior Condensers

New West Mechanical Yard w/ Condensers
NEXT WEEK'S ACTIVITIES
- Complete Texturing of All Walls
- Start Priming Walls
- Continue Ceiling Grid Installation
- Complete New Wood Fencing @ Mechanical Yards
- Cont. Wire Installation in Conduit

- Complete Electric Conduit Installation
New Restroom @ Worship Center Main Foyer

Complete 12' AFF Ceiling Grid @ Southern Bay of Gathering Room
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.