Weekly Project Update

HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATION

Placeholder

Nathan Barry

THIS WEEK'S ACCOMPLISHMENT

    Complete New Mechanical Yard Housekeeping Pads
    Install Temporary Chain-link Fencing @ New Mech. Yards
    Complete Ceiling Grid @ 12' AFF Bays in GATHERING ROOM
    Complete Tape-Float-Sanding of all walls
    Set All but (3) Condensers
    Extend Refrigerant Lines to Exterior Condensers
Excavation 1.jpg

New West Mechanical Yard w/ Condensers

NEXT WEEK'S ACTIVITIES

    Complete Texturing of All Walls
    Start Priming Walls
    Continue Ceiling Grid Installation
    Complete New Wood Fencing @ Mechanical Yards
    Cont. Wire Installation in Conduit
Excavation 1.jpg
    Complete Electric Conduit Installation

New Restroom @ Worship Center Main Foyer

Excavation 1.jpg

Complete 12' AFF Ceiling Grid @ Southern Bay of Gathering Room

LOOK AHEAD SCHEDULE