HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATION

Placeholder

Nathan Barry

THIS WEEK'S ACCOMPLISHMENT

    Start Sheetrock @ Gathering Room Fur-Downs
    Start Sheetrock @ North & South Walls of Gathering Room
    Continue Wall Framing @ Kitchen Area
    Completed U/G Plumbing - ready for COA PLUMBING INSPECTION
    Demo AHU 7.1 and 7.2
    Start Extending Refrigerant Line Sets for New AHU's
Excavation 1.jpg

U/G Plumbing Rough @ Family RR WC-010

NEXT WEEK'S ACTIVITIES

    Continue One-siding Sheetrock @ New Walls
    Complete New Framing @ 1st Floor Restrooms
    Pour-back Slab @ U/G Plumbing
    Continue Electrical Back-boxes & Conduit Rough @ Walls
    Continue Extending Refrigerant Line Sets
Excavation 1.jpg
    Frame for Toilet Accessories

Extending Refrigerant Line Sets to AHU Locations

Excavation 1.jpg

Install Sheetrock @ North Wall of Gathering Room

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.