top of page


Weekly Project Update
HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATION

Nathan Barry
THIS WEEK'S ACCOMPLISHMENT
- Start Sheetrock @ Gathering Room Fur-Downs
- Start Sheetrock @ North & South Walls of Gathering Room
- Continue Wall Framing @ Kitchen Area
- Completed U/G Plumbing - ready for COA PLUMBING INSPECTION
- Demo AHU 7.1 and 7.2
- Start Extending Refrigerant Line Sets for New AHU's

U/G Plumbing Rough @ Family RR WC-010
NEXT WEEK'S ACTIVITIES
- Continue One-siding Sheetrock @ New Walls
- Complete New Framing @ 1st Floor Restrooms
- Pour-back Slab @ U/G Plumbing
- Continue Electrical Back-boxes & Conduit Rough @ Walls
- Continue Extending Refrigerant Line Sets

- Frame for Toilet Accessories
Extending Refrigerant Line Sets to AHU Locations

Install Sheetrock @ North Wall of Gathering Room
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page