top of page


Weekly Project Update
HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATIONS

Nathan Barry
THIS WEEK'S ACCOMPLISHMENT
- Start Slab Demo to uncovering UG Plumbing Piping for new Restrooms
- Continue O/H Electric Conduit Rough
- Start Wall Demo
- Continue Supply Duct Sealing and Insulation Wrap
- Start New Wall Framing
- Continue Ceiling Fur-Downs in Gathering Room

Slab Demo for Plumbing @ New Restrooms
NEXT WEEK'S ACTIVITIES
- Complete Ceiling Fur-Down Framing
- Continue New Wall Framing
- Start U/G Plumbing Rough @ New Restrooms
- Complete All Wall Demo
- Continue Electric Conduit Rough

- Continue Re-installing Hollow Metal Frames
Basement Renovation Floor Plan

GATHERING ROOM Ceiling Fur-down Framing
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page