top of page


Weekly Project Update
MARTIN CRUMPTON

Pat Tims
THIS WEEK'S ACCOMPLISHMENT
- CARPET INSTALLATION
- LVT INSTALLATION
- COVE BASE INSTALLATION
- FINAL CLEAN
- TENANT MOVE IN
-

OFFICE COMPLETE
NEXT WEEK'S ACTIVITIES
- PUNCH LIST
- MILLWORK UNDER CONSTRUCTION
- ROLLER SHADES ON ORDER
-
-

-
OPEN AREA COMPLETE

MOVE IN SATURDAY
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page