THIS WEEK'S ACCOMPLISHMENT

    Installed storm drain on the east side of the building that will carry rainwater to the pond.
    Completed drilling and poured concrete in all piers.
    Began grade beam excavation.
Excavation 1.jpg

Installing steel reinforcement down in the ground.

NEXT WEEK'S ACTIVITIES

    Complete perimeter grade beam excavation.
    Set form panels for grade beams.
    Receive rebar and void form boxes for grade beams.
Excavation 1.jpg

Storm drain that will take rainwater from the roof to the pond.

Excavation 1.jpg

Excavating soil so grade beams can be formed .